WC Renovation Quote

Customer Name: Becki Evans

Project Address: 2 Bute Walk, N12QX

Quote Date: Sun Dec 14 2025 20:20:40 GMT+0000 (Coordinated Universal Time)

Quote Reference: 33

1. Labour Work

Demolition:
- Removal of existing tiles.
- Removal of current toilet).

Plumbing: Speed Fit and Solvent Weld
- Re-plumbing of the waste pipe where necessary to allow for the new layout. - Re-plumbing of the hot and cold water to allow for the new layout.

Carpentry & Drylining:
- Install floorboards to allow tiling.

- Replacing all damaged plasterboards.

Tiling:
- Tiling of the walls and floor as per 3D design.

Fixtures:

- Installation of a new toilet with a vanity unit cistern.

Skimming & Painting:

- Anti-mould, waterproof paint on ceiling and walls.

Total Labour Price: £3000 - Discounted

2. Labour Materials (Estimate)

Includes plasterboards, adhesives, grout, fixings, plywood, levelling compound, waterproofing materials, etc.

Receipts will be collected and shared at the end of the project for reimbursement. 

Estimated Price: £300

3. Tiling Area / Tiles Needed

- Wall Tiling Needed: 6 m2.

- Floor Tiling Needed: 2 m².

*As per customer-selected tiles and 3D design layout. *

Tiles Price: N/A - To Be Selected By Customer..

4. Fixtures and Fittings

Fixtures and fittings to be supplied by the customer as requested.

Our Proposal:

Victorian Plumbing Basket: LINK

Victorian Plumbing Basket Code: J4R7T

Trade Price: £422.05

5. Rubbish Collection (Estimate)

All waste will be stored safely until the end of the project. A quote will be obtained based on a picture and shared for approval prior to disposal.

Estimated Price: N/A - Will be disposed with the rest of the rubbish.

Overall Estimate - highly discounted

Labour Work: £3000

Building Materials: £300

Tiles Price: N/A - To Be Selected By Customer..

Fixtures and Fittings: £422.05

Rubbish Collection: N/A - Will be disposed with the rest of the rubbish.

TOTAL ESTIMATED PRICE: £3722.05

3D Designs And Previews

*Rendered 3D visuals will be shared via email for high-resolution viewing. *


Please note that the 3D Desings are for illustration purposes only and are intellectual property of STEP-AHEAD Renovation & Designs LTD

3D Design Walkaround

Warranty & Payment Terms

  • 2-year warranty on all labour work.
  • Payments accepted via card, transfer, or cash.

 

Our Standard Payment Structure:
(Based on the Labour Work Price).

Commitment Payment – 30%:
This payment secures your project date and enables us to assist further with fixture selection, ordering, etc.

Milestone 1 – 30%:
Due upon completion of plumbing, plastering, and waterproofing, with walls prepared for tiling.

Milestone 2 – 30%:
Due upon completion of tiling and installation of the bathtub/shower tray.

Upon Customer Approval – 10%:
Due once you are satisfied with the work and snagging issues are resolved.

 

The Payment Structure is based on the Labour Work Price.

 

Prepared by: Ivan Georgiev
Position: Project Manager