Bathroom Renovation Quote
Customer Name: Chris Doughty
Project Address: 78C Wilberforce Road, N4 2SR
Quote Date: Sun Jan 04 2026 14:37:23 GMT+0000 (Coordinated Universal Time)
Quote Reference: 42
1. Labour Work
This section outlines all labour
included in your bathroom
renovation.
It covers demolition, plumbing
alterations, carpentry, electrics,
waterproofing, tiling, installation of
fixtures, and final finishing works.
Demolition:
- Removal of existing tiles
- Removal of current fixtures (sink,
bathtub, etc.)
Plumbing: Speed Fit and Solvent
Weld
- Re-plumbing of the waste pipe
where necessary to allow for the new
layout. - Re-plumbing of the hot and
cold water to allow for the new layout.
- Re-plumbing of the radiator pipes
to allow for the new layout.
Carpentry & Drylining:
- Install floorboards to allow tiling.
- Replacing all water damaged
plasterboards.
- Bulding of a new box to allow for the
wall-hung toilet.
- Building of a new ceiling wit
plasterboard.
- Installation of a new window above
the door + make good both sides.
£500
Electrical:
- Wiring of new ceiling lights
downlights.
- Wiring of the new led mirror cabinet.
- Wiring of a new extractor fan.
Waterproofing:
- Sealing joints and angles.
- Full waterproofing with tanking kit around the shower area.
Fixtures:
- Installation of a new wall-mounted vanity unit with basin and a tap. 600mm
- Installation of a new shower tray and enclosure.
- Installation of a new wetroom tray and screen.
- Installation of a new bathtub and screen.
- Installation of a new bath filler.
- Installation of a new shower mixer.
- Installation of a new toilet and a cistern.
Skimming & Painting:
- Anti-mould, waterproof paint on ceiling and walls.
Total Labour Price: 123123 - Discounted
2. Labour Materials (Estimate)
This section covers materials required to carry out the labour, such as:
plasterboards, fixings, adhesives, grout, levelling compound, waterproofing materials, plywood, sealants, and similar consumables.
These materials are purchased as needed during the project to ensure correct installation and quality.
All receipts will be collected and shared at the end of the project, and the final amount will be adjusted based on actual cost.
This is an estimate, and you only pay for what is used.
Estimated Price: 123
3. Tiling Area / Tiles Needed
We have calculated the total tiling area required for your bathroom based on measurements and the agreed 3D design.
• Wall tiling required: 19 m²
• Floor tiling required: 4.5 m²
You can copy and paste these measurements directly into any tile supplier’s website (for example: Topps Tiles or your preferred retailer) to calculate how many boxes you need.
💡 We have a 10% discount available with Topps Tiles, which you are welcome to use.
Tiles Price: 123333
4. Fixtures and Fittings
To make this easier, we have prepared a recommended basket that matches your design and layout.
You can either:
• Open the link and order directly
• Or enter the provided basket code on the Victorian Plumbing website.
You are free to choose alternative products if you wish - just ensure dimensions and compatibility match the design.
Our Proposal:
Victorian Plumbing Basket: https://www.victorianplumbing.co.uk/basket?retrievalCode=8VDDX
Trade Price: 123123
5. Rubbish Collection (Estimate)
All waste will be stored safely until the end of the project. A quote will be obtained based on a picture and shared for approval prior to disposal.
Estimated Price: 333
Overall Estimate - highly discounted
Labour Work: 123123
Building Materials: 123
Tiles Price: 123333
Fixtures and Fittings: 123123
Rubbish Collection: 333
TOTAL ESTIMATED PRICE: £370035
3D Designs And Previews
*Rendered 3D visuals will be shared via email for high-resolution viewing. *
Please note that the 3D Desings are for illustration purposes only and are intellectual property of STEP-AHEAD Renovation & Designs LTD
3D Design Walkaround
Warranty & Payment Terms
- 2-year warranty on all labour work.
- Payments accepted via card, transfer, or cash.
Our Standard Payment Structure:
(Based on the Labour Work Price).
Commitment Payment – 30%:
This payment secures your project date and enables us to assist further with fixture selection, ordering, etc.
Milestone 1 – 30%:
Due upon completion of plumbing, plastering, and waterproofing, with walls prepared for tiling.
Milestone 2 – 30%:
Due upon completion of tiling and installation of the bathtub/shower tray.
Upon Customer Approval – 10%:
Due once you are satisfied with the work and snagging issues are resolved.
The Payment Structure is based on the Labour Work Price.
Prepared by: Ivan Georgiev
Position: Project Manager
Step-Ahead Renovations & Designs